Back to group MHA10SN

Organisational communication (A0088), 10 cr

Implementation plan (PDF), 4 pages

Implementation
MHA1111
Semester
1/2011-2012
Dates
29 Aug 2011–19 Dec 2011
Type
AMMATILLISEN OSAAMISEN MUODOSTUMINEN (A012)
Group
MHA10SN
Campus
Laurea Leppävaara
Language of instruction
English
Teachers
Henriksson Kristina (Vastuuopettaja), Rönkä Ilona (Muu opettaja)
Lecturers
NN
Status
Ready
Show text version
                                                                                                                       1/4
TOTEUTUSSUUNNITELMA Valmis



 Opintojakso                             Organisational communication (A0088), 10.0
 Toteutus                                MHA1111: 1/2011-2012 (29.08.2011 - 19.12.2011)
 Tyyppi                                  AMMATILLISEN OSAAMISEN MUODOSTUMINEN (A012)
 Ryhmät                                  Ensisijainen: MHA10SN Muut:
 Projektissa mukana
 Luennoitsijat                           NN
 Osallistujamäärät                       Minimi: Maksimi:
 Ilmoittautumisaika                      23.05.2011 08:00 - 05.06.2011
 Pääsääntöinen toteutusajankohta
 Soveltuvuus                             Vaihto-opiskelijoille: Kyllä Vapaasti valittaviin: Ei Avoimen opisk: Ei Soveltuu
                                         virtuaali-AMK:n opintoihin: Kyllä

 Opettajat                               Henriksson Kristina (Vastuuopettaja), Rönkä Ilona (Muu opettaja)
 Kampus                                  Laurea Leppävaara
 Pääsääntöinen toteutuspaikka
 Toteutustapa                            Muu toteutustapa, Projekti/Hanke/T&K, Verkko/virtuaali Kieli: englanti Virtuaalisuus:
                                         2 op T&k-integraatio: 7 op
 Toteutusluokka
 Painoalat
 Arviointi viimeistään                   19.01.2012 Suoritusmateriaalin arkistointi päättyy: 19.12.2012
 Tenttipäivät

 Opintojakson suoritettuaan              *plan, implement and evaluate an organisation’s communications in English
 opiskelija osaa                         *communicate in English as experts
 Edeltävät opinnot
 Edeltävät opinnot, lisätietoja          The student has passed the level test or successfully completed the remedial course in
                                         English.
 Keskeinen sisältö                       Organizational communication

Oppimistapahtumat
 Pvm              Klo       H     Aihe              Sisältö                                      Tila              Opettajat
 05.09.2011       12-16     4     Teamwork,
                                  theory task
 06.09.2011       9-12      3     Teamwork,         No contact lesson. Teams work on their
                                  theory task       theory task according to instructions
                                                    received by email and found in Optima.
 12.09.2011       12-16     4     Teamwork,
                                  project plans
 13.09.2011       9-12      3     Introduction,     First meeting with teachers.
                                  presentations
                                  of theory task,
                                  lecture,
                                  project task
                                  etc
 19.09.2011       12-16     4     Teamwork,
                                  continue with
                                  theory base
 20.09.2011       9-12      3     Teamwork,
                                  continue with
                                  theory base


SoleOPS 3.5.5 Opetustarjonta © 2005-2016 Solenovo Oy
                                                       2/4
TOTEUTUSSUUNNITELMA Valmis



 26.09.2011   12-16   4    Teamwork,
                           continue with
                           theory base,
                           project work
                           and project
                           meetings;
 27.09.2011   9-12    3    Guidance,
                           Project work
                           and project
                           meetings.
 03.10.2011   12-16   4    Project work
                           and project
                           meetings.
 04.10.2011   9-12    3    Project work
                           and project
                           meetings.
 10.10.2011   12-16   4    project work
                           and project
                           meetings.
 11.10.2011   9-12    3    Guidance,
                           interview
                           themes to be
                           approved.
                           Interviews
                           this week or
                           the next.
 18.10.2011   9-12    3    Project work
                           and project
                           meetings.Continue
                           with theory
                           base and
                           analysis of
                           results
 17.10.2011   12-16   4    Project work
                           and project
                           meetings.Continue
                           with theory
                           base and
                           analysis of
                           results
 25.10.2011   9-12    3    Guidance,
                           Project work
                           and project
                           meetings.
 24.10.2011   12-16   4    Project work
                           and project
                           meetings.
 01.11.2011   9-12    3    Project work
                           and project
                           meetings.
 31.10.2011   12-16   4    Project work
                           and project

SoleOPS 3.5.5 Opetustarjonta © 2005-2016 Solenovo Oy
                                                       3/4
TOTEUTUSSUUNNITELMA Valmis



                           meetings.
 08.11.2011   9-12    3    Report
                           writing,
                           project work
                           and meetings.
                           Deadline
                           interim report
                           Friday noon.
 07.11.2011   12-16   4    Report
                           writing,
                           project work
                           and meetings.
                           Deadline
                           interim report
                           Friday noon.
 15.11.2011   9-12    3    Guidance,
                           Project work
                           and project
                           meetings.
 14.11.2011   12-16   4    project work
                           and project
                           meetings.Continue
                           developing
                           your reports.
 22.11.2011   9-12    3    Project
                           presentations.
                           All present.
                           Peer
                           evaluation.
 21.11.2011   12-16   4    project work
                           and project
                           meetings.Continue
                           developing
                           your reports.
 29.11.2011   9-12    3    Competence
                           essay. All
                           present.
                           Deadline
                           report 30.11.
 28.11.2011   12-16   4    Finalizing
                           report.
                           Deadline at
                           14.00 hours.
                           Team member
                           evaluation
                           deadline
                           01.12.
 06.12.2011                Teachers
                           compiling
                           evaluations
 13.12.2011   9-11    2    Discussions,
                           feedback,

SoleOPS 3.5.5 Opetustarjonta © 2005-2016 Solenovo Oy
                                                       4/4
TOTEUTUSSUUNNITELMA Valmis



                           results.